When using Job Entry - Get Details and appending Materials, the sequencing in which the subassemblies are appended onto the job is different to the sequencing in the Method master.
The job that we are appending to only has 3 operations, no material.
When we use the Get details function to get details from Method master, and we Append both Operations and Materials - the operations append ok, but the materials, which in this case are subassemblies, get appended in a strange order.
On the left below is the order in the Job, on the right it shows the order from the Parts / Method master.
Do you know what could be causing this?
Assembling sequencing is quote important for production, is there any way to force it to be appended in the same order as the master?