Worksheet Calculating Material Burden Incorrectly

Material Unit Cost. 5.04
Mtl Burden Rate 15%
Mtl Burden Unit Cost = .756
This shows correctly on the Manufacturing Tab under materials

Go to the worksheet and it shows this for 500 units
$37.80 which should be .756 x 500 which equals 378.
Print out of the worksheet with details shows the Mtl Burden Unit cost to be .0756 which moves the decimal to make it $37.80

Is there something I am missing. Is this an Epicor Issue?