Question

10.2.500 Scheduling Question

  • 12 October 2021
  • 0 replies
  • 35 views

Userlevel 1

We currently have our Production calendars setup for certain number of hours during the week but have found that we need to have at least one hour set over the weekend so that subsequent ops schedule correctly.

When we run a query on job operations, we see that on closed\completed operations, some jobs are showing "open hours" for those jobs but the hours value is 0. When going to schedule subsequent operations, it looks like the start date \ hour is looking at the next available start date \ hour of that completed op showing open but at 0. If a machine has exceptions to shut off all time for a week or two (machine crash, etc) the subsequent ops are not scheduling until the day that the calendar for that machine is showing available again.

Do we have a setting somewhere that is driving this?

Thanks

Melissa