Question

Having trouble with Schedule

  • 12 October 2021
  • 3 replies
  • 100 views

Does anyone know why my jobs are running 13 times in this Resource Group?  I’m sure it has something to do with the fact that we have 13 Resources set up in this group. Every job scheduled in this group looks like this!

I am picking up where someone left off and not having any fun trying to figure out why Epicor does what it does.

 

Thank you,

Tracy

Planner/Scheduler

 

 


3 replies

I would first review Operation setup.

Any chance the Operation is linked to each Resource in the Group rather than the Resource Group itself?

Hi Tracy,

Do you have the operation setup to use 13 scheduling blocks? Using 13 scheduling blocks would indicate you want to use all 13 of the resources within that resource group. 

That was it - all fixed now!

Thank you!