Hello,
We are running into a scenario where we want Epicor to suggest the soonest we can produce items. We work in a configurable environment and would want our top level products to take into consideration lower level part lead times and so have marked them as constrained.
We work in a plan as assembly environment.
In this example below, our scheduling engine seems to be ignoring that one product will be coming in later than the top level requires the material.
We don’t have raw materials to build this part and as such it has pushed MRP jobs into October of 2021.