We are using the Kinetic standard RFQ process, even though it is and old program, it is working well for our needs. The one problem we have is with Purchased direct items, when we create the PO from the RFQ it is updating the material unit cost. We would prefer this did not happen as we want to leave our original cost estimate in there. Any suggestions? Thank you 