PO Due Date Management

  • 10 March 2022
  • 3 replies
  • 587 views

Need to retain original PO due dates, capture Supplier confirmed Estimated Ship dates, communicate to production delays caused by late deliveries.  By using the Epicor Kinetic system only, not plug ins or spreadsheets, what is the best practices everyone has derived?

What about Supplier Performance tools? Are there good tools housed in Epicor Kinetic? Is everything a plug in or done externally to the system? 

Has anyone come up with a best practice to confirm that PO’s have been acknowledged by suppliers other than manually checking the confirmed check box in PO Entry?

Are there good learning modules that I am missing that have covered all of these topics? 

Joni Dahl

Iracore, Material Manager

218-362-8786


3 replies

For the Due Date I think the best way is to use the Promise Date to store the Date that the supplier says they can deliver and do not move the Due Date. But we struggle with this because our buyers like to move the Due Date instead. One of the problems with moving the Due Date is then the supplier performance reporting is not accurate because we use the Due Date to calculate Days Early/Late on our reporting. If the Buyer and Supplier both agree it’s ok to move the Due Date then that’s fine. But the Due Date often gets moved when we get an update from the supplier that it’s going to be late and the Buyer wants to reflect that, when this happens the reporting will not be correct since the Due Date is no longer the date we wanted it... in this situation they should be using the Promise Date.
 

The Promise Date does display in other areas like Time Phase

 

For supplier performance reporting we have created our own reports that show Days Early/Late for each release and a summary of to show the total number of Early, Late, and On Time receipts. This reporting uses the Early/Late buffer in the supplier master.

 

For acknowledgements there are additional modules or 3rd party addons that leverage a supplier portals to keep track of supplier communication like acknowledgements. There are two different types of models/addons for MRO and Raw Material.

Userlevel 3

Epicor is written with the expectation that supplier delivery dates will move.

The due date is what will drive scheduling, available to promise, and MRP.

If you don’t move the due date, the standard system tools will not show you that you will not make your delivery.

 

The promise date is available to measure the performance of delivering on time.  

Time phase uses the due date to show the projected balance based on when Purchase orders are due in to inventory or the job.

 

Very recently we just had this discussion on which way to use this and what you are saying Bruce is probably why the buyers have been reluctant to use the Promise Date. The trouble is Buyers don’t remember to populate the Promise Date with the original due date either so the Promise Date doesn’t work at all right now for reporting for us. I’m thinking maybe we need to use a BPM to populate the Promise Date when they first enter a Due Date.

Reply