Question

Change Supplier on PO

  • 28 June 2021
  • 7 replies
  • 288 views

  • Participating Frequently
  • 8 replies

I have an open approved purchase order and need to change the vendor/supplier. It appears to be greyed out but it is not tied to a sales order. What else would lock the supplier so that it can’t be changed? 

 


7 replies

Userlevel 2

Unapprove it?

sorry I should have stated that when I unapprove the PO, I still can’t change the supplier. 

Userlevel 2

I’d start looking at the line/release detail. Purchase to job, subcontract, something like that.

 

Joe

Userlevel 1

also, has there been a receipt?

Yes there was a receipt against the order. I set the same situation up in our test environment and i could still change the supplier even after the receipt.

Are you an authorised user of the buyer?

Userlevel 3

Wondering if you also have received payment against the receipt.

Reply