Hello,
We are struggling with Epicor’s planning functionality. We use plan as assembly for all our BOMs, however the system is unable to consider extended lead times on lower level constrained material. Please see an example below.
This material should be constraining it.
We cannot add fixed mfg lead times as sometimes we have the lower level components in stock, then it could take us 1 day to manufacturer all pieces required. Due to COVID, all our items have extended lead times and we have locked our POs. Global Scheduling also does not help with the process.