Does anyone have any experience with tis functionality? We are having difficulty making it work,
Userlevel 1
We do this on a somewhat regular basis. What are the specific issues that are not working?
There are a couple of things that can make it go awry. Mostly making sure that the original job and the subordinate job reference the correct warehouses so that that demand is correct. We’ve had some issues where the subordinate job does not reflect a planner--though I think that is fixed in 10.2. Lastly, once you receive the job into the top level job it does not show as issued complete--though it will see it as complete if you are auto-closing. You just don’t get the green check.