We have a part that needs to have it’s battery charged before assembly. We can only charge 15 batteries at a time. How can I account for this time in the schedule when the quantity required is more than 15?
Userlevel 2
One idea is to use a resource group with 15 resources. On the operation to charge the batteries use the resource group as the scheduling constraint.
Mike
I haven’t used the daily production capacity and concurrent capacity settings in Resource Group and Resource maintenance, but there these are tools for working with quantity constraints. Maybe this would work?
Thanks for the replies. Mike - I will try that setup now.
How do I setup the operation to use the resource group as a scheduling constraint?