Hello!
We have an issue with Scheduling and I’m thinking we can’t be the first company to have this type of problem; we run the same part number on back to back jobs and only need the set up hours on the first job. The subsequent jobs carry the set up time which we don’t use, and it skews our production schedule. (These parts are made complete in one operation.)
I’m sure we could delete the set up ops on the subsequent jobs during job creation, but was wondering if there was an option in Epicor that would fix this issue without additional steps required of the planners.
Thanks!
Tracy