Multi-plant folks, with Operations master records different between plants: Is there a way of loading the single-plant operations only in the plant where they exist?
I used DMT for the loading of the separate operations into the two plants, but when I do it manually in the Operation program the same problem still exists. When I enter a new Operation and its scheduling requirement in a given plant, it also appears without the scheduling requirement, in the other plant. In the Operation (Maintenance) program, when I open one of these “not in this plant” operations, error messages are displayed saying, “a scheduling requirement must exist.”
10.2.700. Can anyone point me in the right direction? We have two plants that have very different resources and capabilities, and we’ve attempted to keep the operations, resources and resource groups separate between the plants.