Hi,
I am trying to figure out if it is possible to get MRP suggestions per SO instead of by Date. We currently use Forecast entry to enter our Customers demand. We also enter SOs before we run MRP daily. But if I run MRP after enter 5 SO for the same product due the same day I just get 1 MRP suggestion when I really have to make 5 jobs so they ship and bill per the POs we receive from our customer. Also I have to have these 5 orders as some of these jobs take a lot of run time on a machine so we try and break them up for production planning purposes. Am I just missing a step somewhere in MRP or a setting feature? or does Epicor not work like that?
Currently I am just stealing any other MRP suggestions that come up for later dates or if there is none I have to create a quick job to enter these then just re run MRP to pull the forecast demand in after I firm up my jobs.
Best answer by tshoemaker